Sunday Stucco and Sprinklers

— SjG @ 6:29 pm

The crew was working on Saturday too, so today’s the first time I’ve got an updated view of the stucco.

Meanwhile, the sprinklers up front were not working correctly. I’m no Hercule Poirot, but I was able to get to the cause of the problem. And fix it.

Filed in:

Tue, 23 Mar 2021

Start of Stucco

— SjG @ 6:03 pm

This morning started with a lot of heavy machinery to bring the stucco and sand, and to deliver the mixer and start it all going. The stucco is being applied by hand. Perhaps the surface will be sprayed on? It remains to be seen.

Filed in:

Mon, 22 Mar 2021

Additional Drywall

— SjG @ 5:52 pm

Over the weekend, I looked around the unit and saw the progress on the drywall and the shower. These pictures don’t really seem all that different, but a lot of detail work is being done in corners and edges. And, of course, the shower pan hadn’t been there before!

There was a drywall inspection, where they evidently audit the size and number of screws used to secure it.

Filed in:

Sun, 21 Mar 2021

The Power

— SjG @ 5:39 pm

As foretold, the power was out for half the day Saturday while the team replaced the old panel with a new one. Sadly, I don’t have any good pictures from before. The power was already a bit complicated by the solar cutoff switch and meter. Now, the panel’s been replaced, and there’s a big box with our meter and a spot for the ADU’s meter.

Filed in:

Thu, 18 Mar 2021

Further Adventures in Drywall

— SjG @ 9:33 pm

More progress today. Now the rumor is the power will be out tomorrow or the next day.

Filed in: