Progress Report

— SjG @ 6:52 pm

It’s been a while since I’ve posted on the ADU. Not a lot of visible changes are happening, but there’s a lot going on behind the scenes. The A/C unit installation has started, and some of the interior electrical tasks have been completed. We’re starting to tidy some of the garden areas and get things in order for our tenants!

In terms of schedule, we expect the cabinets to arrive in the next 30 days, after which the kitchen and bathroom fixtures will be installed. We’re looking at Certificate of Occupancy to be issued by LADBS in July, and an August move-in for the renters. The new tenants will miss the peak spring bloom of the garden, but they’ll still get to enjoy the butterflies.